Key Principles at a Glance 6 points
  • The Saturday routine is the ship's planned maintenance programme for testing emergency and safety equipment on a fixed schedule — every Saturday, fortnightly and monthly — so equipment is proven ready when needed.
  • Every-Saturday checks include the fire detection system, air and foam equipment, the general alarm system, funnel flaps, lifeboat engine, emergency fire pump, emergency air compressor and the oily water separator with its 15 ppm indicator.
  • Fortnightly checks include emergency batteries, emergency lighting and the emergency steering gear.
  • Monthly checks include the CO2 bottles and system, emergency/remote stops (M/E quick closing valve, E/R blower, E/R pump, accommodation blower), emergency bilge suction valve, unused valves (ship-side, sewage plant, isolating), portable electrical tools, main and auxiliary engine safety devices, M/E manoeuvring, cargo gear limit switches, boiler safety valve and the alarm systems.
  • Each check is assigned to a responsible officer (Electrical Officer, Second, Third or Fourth Engineer), and the results are recorded in the planned maintenance system.
  • A properly run Saturday routine is the direct evidence that emergency equipment and safety devices are maintained and operational — a key surveyor and PSC expectation.

1. What is the Saturday Routine?

The Saturday routine is the ship's weekly planned maintenance programme for testing and checking emergency and safety equipment. Work is scheduled by frequency — every Saturday, fortnightly and monthly — and each item is assigned to a responsible engineer.

Why It Matters:

  • Emergency equipment sits idle for most of a voyage; the routine proves it will work when it is suddenly needed.
  • Testing at sea (away from port restrictions) confirms the equipment is operational under realistic conditions.
  • The records generated are the evidence a surveyor or Port State Control officer uses to confirm the planned maintenance system is effective.

Who Does What:

  • Electrical Officer — electrical/electronic safety systems (fire detection, general alarm, emergency batteries and lighting, remote stops, safety devices, alarm circuits).
  • Second Engineer — engine-room machinery safety (CO2, air & foam, emergency steering gear, remote stops, M/E manoeuvring, unused valves).
  • Third Engineer — lifeboat engine, boiler safety valve (with Electrical Officer).
  • Fourth Engineer — funnel flaps, emergency fire pump, emergency air compressor, emergency bilge suction valve, auxiliary engine safety (with Electrical Officer).
SATURDAY PLANNED MAINTENANCE ROUTINE Every Saturday · Fortnightly · Monthly — test emergency & safety equipment, record the results EVERY SATURDAY Fire detection General alarm Emergency fire pump Lifeboat engine · OWS Air/foam · funnel flaps FORTNIGHTLY Emergency batteries Emergency lighting Emergency steering gear MONTHLY CO2 bottles & system Remote / emergency stops Emergency bilge suction Safety devices & alarms Boiler safety valve Responsible officers: Electrical Officer (electrical/alarms) · 2/E (engine-room safety) · 3/E (lifeboat, boiler) · 4/E (emergency pumps, flaps, bilge suction)
Figure 1: Saturday Routine Overview. Weekly, fortnightly and monthly buckets of emergency/safety checks, each assigned to a responsible engineer, with the results recorded.

2. Every-Saturday Checks

These are carried out every Saturday:

  • Fire Detection System [Electrical Officer] — every Saturday.
  • Air and Foam Equipment [Second Engineer] — every Saturday.
  • General Alarm System [Electrical Officer] — every Saturday.
  • Funnel Flaps [Fourth Engineer] — every Saturday.
  • Lifeboat Engine [Third Engineer] — every Saturday.
  • Emergency Fire Pump [Fourth Engineer] — every Saturday.
  • Emergency Air Compressor [Fourth Engineer] — every Saturday.
  • Oily Water Separator & 15 ppm Indicator [Electrical Officer] — every Saturday.
Why These Every Week?

Fire detection, the general alarm, the emergency fire pump, the emergency air compressor and the lifeboat engine are the first-response items in any emergency. A week is the longest they should sit untested, so they are proven every Saturday. The OWS/15 ppm is checked because it is a daily pollution-control item.

EVERY-SATURDAY CHECKS First-response emergency equipment tested each week Fire Detection System Electrical Officer Air and Foam Equipment Second Engineer General Alarm System Electrical Officer Funnel Flaps Fourth Engineer Lifeboat Engine Third Engineer Emergency Fire Pump Fourth Engineer Emergency Air Compressor Fourth Engineer Oily Water Separator & 15 ppm Indicator Electrical Officer
Figure 2: Every-Saturday Checks. Fire detection, air/foam, general alarm, funnel flaps, lifeboat engine, emergency fire pump, emergency air compressor and the OWS with 15 ppm indicator — each with its responsible officer.

3. Fortnightly Checks

These are carried out fortnightly:

  • Emergency Batteries [Electrical Officer] — fortnightly.
  • Emergency Lighting [Electrical Officer] — fortnightly.
  • Emergency Steering Gear [Second Engineer] — fortnightly.
The Emergency Power Chain

Emergency batteries, emergency lighting and emergency steering gear all depend on the emergency source of electrical power. Fortnightly testing proves that when main power is lost, the emergency supply, lighting and steering are available — the classic "blackout" scenario.

FORTNIGHTLY CHECKS Emergency electrical supply, lighting and steering Emergency Batteries Electrical Officer Emergency Lighting Electrical Officer Emergency Steering Gear Second Engineer Tests confirm that on loss of main power the emergency source, lighting and steering remain available.
Figure 3: Fortnightly Checks. Emergency batteries, emergency lighting and emergency steering gear are proven every two weeks so the ship can cope with a blackout.

4. Monthly Checks

These are carried out monthly:

  • CO2 Bottles and System [Electrical Officer] — monthly.
  • Emergency / Remote Stops [Electrical Officer & Second Engineer] — monthly (M/E quick closing valve, E/R blower, E/R pump, accommodation blower).
  • Emergency Bilge Suction Valve [Fourth Engineer] — monthly.
  • Normally Unused Valves [Second Engineer] — monthly (ship-side valve, sewage plant, isolating valve).
  • Portable Electronic Tools and Equipment [Electrical Officer] — monthly.
  • Main Engine Safety Devices [Electrical Officer & Second Engineer] — monthly.
  • Auxiliary Engine Safety [Electrical Officer & Fourth Engineer] — monthly.
  • Main Engine Manoeuvring [Electrical Officer & Second Engineer] — monthly.
  • Cargo Gear — all Limit Switches [Electrical Officer] — monthly.
  • Boiler Safety Valve [Electrical Officer & Third Engineer] — monthly.
  • Alarms: freezer room, hospital room, bilge, incinerator room and steering gear alarms [Electrical Officer] — monthly.
Surveyor Asks

Surveyors frequently ask: "What do you do on Saturday?" Give the routine by frequency — and remember the two favourites they test: the emergency fire pump (every Saturday) and the emergency steering gear (fortnightly), plus the remote/emergency stops and engine safety devices (monthly).

MONTHLY CHECKS Systems that can wait a month but must still be proven Fire / pollution • CO2 bottles & system • Emergency bilge suction valve • Boiler safety valve • Cargo gear limit switches Stops & safety devices • Emergency / remote stops M/E QCV · E/R blower · E/R pump Accommodation blower • Main engine safety devices • Auxiliary engine safety • Main engine manoeuvring Valves & alarms • Unused valves ship-side · sewage · isolating • Portable electrical tools • Alarms: freezer · hospital · bilge incinerator room · steering gear
Figure 4: Monthly Checks. The CO2 system, emergency/remote stops, bilge suction valve, unused valves, portable tools, engine safety devices, manoeuvring, cargo gear limit switches, boiler safety valve and the various alarm circuits.