General

Topic 12 of 22

Back to General
Tools

Emergency Generator: Testing & Requirements

Learn emergency generator testing, independent starting modes, automatic start and transfer, stored starting energy and essential services supplied.

Published by ChartandKeel Updated

1. Purpose & Starting Modes

  • The emergency generator on a ship provides power in case the main generators fail, creating a dead ship / blackout condition.
  • According to the general requirement, at least two modes of starting an emergency generator should be available.
  • The two modes should be — battery start and hydraulic or pneumatic start.
  • Port State Control (PSC) might detain a ship or provide some time to correct any deficiency found if the second mode of starting is not operating.

Why two modes? If the battery is flat, the generator must still start by hydraulic/pneumatic energy; if that fails, the battery remains. Two independent stored-energy sources guarantee the emergency generator can start when the ship has blacked out — which is exactly when it is needed.

EMERGENCY GENERATOR — PURPOSE & STARTING MODES Provides power on blackout • Two modes: battery start + hydraulic/pneumatic start EMERGENCY GENERATOR MODE 1 Battery start MODE 2 Hydraulic / pneumatic start PSC may detain the ship or allow time to correct the deficiency if the second starting mode is not operating. Both stored-energy sources must be kept energised and ready at all times.
Figure 1: Purpose & Starting Modes. The emergency generator supplies power on blackout and must have two starting modes — battery and hydraulic/pneumatic — or PSC may detain the ship.

2. Testing Schedule

Routine weekly check:

  • Carry out the routine start test at the interval in the vessel’s procedure. Where safe and provided for, the test may simulate loss of normal power and prove the automatic start signal and transfer arrangement.

Other tests at the intervals in the vessel’s approved procedure:

  • Prove each independent starting mode and the automatic start/changeover at the interval and by the method specified in the vessel’s approved testing procedure.
  • Supplement short no-load runs with a proper load test at the prescribed interval; only a load test demonstrates the prime mover, alternator, breaker and interlocks under load.
FrequencyTestPurpose
Weekly routine checkStart test and, where prescribed, simulated mains failureProve the selected start and automatic transfer sequence
As specified by vessel procedureIndependent second starting mode and automatic changeoverProve all installed starting and transfer functions
At prescribed intervalsControlled load testProve the set, breaker and interlocks under load

Remember the pattern. Weekly testing commonly includes a start run and may simulate loss of normal power. The exact second-mode, automatic-changeover and load-test intervals come from the vessel’s approved procedure. A brief no-load run does not prove rated-load performance.

Indexer Figure 4.3(b) flow chart for routine emergency-generator testing, including automatic start, breaker transfer, power established and return to normal supply
Figure 4.3(b): The test flow checks standby selection, the tie-breaker signal, engine start and speed, voltage, emergency-breaker closure, and restoration. Carry it out using the ship’s approved test method and safeguards.

3. Battery & Hydraulic Start Procedures

Procedure for Battery Start:

  1. Go to the emergency generator room and find the panel for the emergency generator.
  2. Put the switch on test mode from automatic mode. The generator will start automatically but will not come on load.
  3. Check voltage and frequency in the meter.
  4. Run it for the duration specified by the approved test procedure; monitor exhaust temperature and other operating parameters.
  5. Check the sump level.
  6. For stopping the generator, put the switch in manual and then stop the generator.

Procedure for Hydraulic Start:

  1. Put the switch in manual mode as above and check the pressure gauge for sufficient oil pressure.
  2. Open the valve from the accumulator to the generator.
  3. Push the spring-loaded valve and the generator should start.
  4. Check voltage and frequency.
  5. Run the generator for the duration specified in the approved procedure and check the exhaust temperature and other parameters; check the sump level.
  6. For stopping, use the manual stop button from the panel.
  7. After stopping the generator, pressurise the hydraulic accumulator to the desired pressure.
  8. Close the valve from accumulator to generator.

Don't forget the accumulator. After every hydraulic start, the accumulator must be re-pressurised and the supply valve closed — otherwise the second starting mode will not be ready next time. This is a common PSC finding.

Figure 3: Battery and hydraulic emergency-diesel startersTwo physical generator starting arrangements: battery contactor and electric starter above; gas-precharged accumulator, pump, valves, hydraulic starter and reservoir below. Both engage the engine flywheel; test behavior is explicitly vessel-specific.Emergency diesel starting · two representative arrangementsMaker-specific alternatives: do not infer that every generator has both systems.BATTERY · electrical starterDiesel engineAlternatorBattery+ −ContactorStarter pinion → ring gearStart demand / test controls Use vessel-specific procedureHYDRAULIC · charged accumulator drives the starter motorDiesel engineAlternatorPrecharge gasOilReservoirPumpCheckStart valvePressureHydraulic starterRelief to tankTest mode, transfer/load behavior and starting sequence are vessel-specific. Check indicated voltage / frequency and restore AUTO readiness after an approved test. Hydraulic isolation, residual pressure, recharge and starter disengagement follow the maker.
Figure 3: Start procedures for the battery and hydraulic arrangements fitted to this example. Follow the vessel procedure for test mode, load, running duration and accumulator reset.

4. Automatic Start, EGS Requirements & Power Supplied

Procedure for Automatic Start:

  • A breaker connects the Emergency Switch Board (ESB) and the Main Switch Board (MSB), with an interlock so that the emergency generator and the main power cannot be supplied together.
  • To test, simulate by opening the breaker from the tie line, which can be done from the MSB or the ESB panel.
  • After opening the breaker, the emergency generator starts automatically on batteries and supplies essential power to the machinery and pumps connected to the ESB.
  • To stop, the breaker is closed again and, due to the interlock, the generator becomes off load; put the switch to manual mode and press stop.

Requirements for Emergency Generating Sets:

  • Requirements involve starting in cold condition and starting energy-storing devices.
  • Emergency generating sets shall be capable of being readily started at a temperature of 0°C; if impracticable or lower temperatures are likely, heating arrangements shall be provided.
  • Each automatically started set shall have approved starting devices with stored energy for at least three consecutive starts.
  • A second source of energy shall be provided for an additional three starts within 30 min, unless manual starting is demonstrated to be effective.
  • Stored energy maintenance: electrical and hydraulic systems from the ESB; compressed air from main/auxiliary receivers through a non-return valve, or an emergency air compressor (if electric) from the ESB; all starting/charging/energy-storing devices located in the emergency generator space.
  • Where automatic starting is not required, manual starting is permissible (manual cranking, inertia starters, manually charged hydraulic accumulators, powder charge cartridges) where demonstrated effective.

Power Supplied by the Emergency Generator:

  • On failure of the main power generation, the emergency/standby system ensures essential machinery keeps the ship operating; batteries, an emergency generator, or both may be used.
  • Essential systems supplied include: (a) steering gear; (b) emergency bilge and fire pumps; (c) watertight doors; (d) fire-fighting system; (e) navigation lights and emergency lights; (f) communication and alarm system.
  • The emergency generator is normally located outside the machinery space, to avoid situations where access to the engine room is not possible; a switchboard in the emergency generator room supplies the essential machinery.

Surveyor asks: "How do you test the emergency generator?" Describe the vessel’s routine schedule and approved test procedure, then explain the independent starting arrangements, applicable stored-energy capacity and the essential services supplied.

Figure 4: Automatic emergency supply and source isolationReused emergency-power single line shows isolated main switchboard, dedicated emergency generator and starting energy, emergency switchboard feeding safety loads, transitional battery and an illustrative start-air recovery consumer.Automatic emergency supplyMain machinery spaceEmergency generator spaceGDG 1GDG 2MSB • deadQmQt OPENGEDGFuelDedicated start energyESB • liveInterlockSafety loadsSeparate spaceTransition batteryAC/DCCritical subsetBBMMReceiver / compressor
Figure 4: Automatic Start, EGS Requirements & Power Supplied. The ESB–MSB breaker/interlock automatic test, the 0°C / 3+3 start rules, and the essential services supplied by the E/G outside the machinery space.
Emergency generator panel with meters and lamps
Reference photo: the E/G panel — meters and lamps as surveyed.
Emergency generator start selector in hand
Reference photo: the start selector in hand — the weekly test position.
Emergency generator prime mover end
Reference photo: the prime mover end.
Emergency generator meters with test instruction
Reference photo: meters with the test instruction posted alongside.